Nubaria Power Plant III 2x750 MW CCP.
Owner: West Delta Electricity Production Company
(WDEPC).
Main Contractor: HAS & CCC "MSD"
Quantity: 3500 Tons
Execution Period: 6 Months 2008-2009
ARCONS Scope of work Installation of HRSG steel structures building CTG, STG, Pump House ..etc. for 2x750 MW Combined Cycle Project.